Mr. Bui Van Quang, Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People’s Committee, visited Cam Khe on October 3 to review the development of site clearance, investment in technical infrastructure building, and industrial park resettlement zones.
Chairman Bui Van Quang conclused the meeting.
Duc Anh Construction Joint Stock Company is investing in the infrastructure construction project at Cam Khe Industrial Park. The overall construction area in Thanh Nga, Son Nga, Sai Nga communes (now Cam Khe town) and Xuong Thinh commune, Cam Khe district is 450 hectares, of which 427 hectares are for industrial park infrastructure building.
Provincial Police Director Nguyen Minh Tuan remarked on the project’s required counting and forced land recovery.
Cam Khe district authorities revealed findings and intentions to expedite site clearing efforts at the Cam Khe Industrial Park.
Despite the fact that Cam Khe district and relevant agencies have increased the project implementation direction, site clearing progress has not matched the needs and goals. The industrial park’s biggest issue is that it is located on 183 hectares of cleared agricultural land, but the infrastructure cannot be completed because there are still 26/217 households subject to resettlement that have not coordinated to review and count, as well as 35 households and individuals. There is agricultural property that has been compensated for palm trees but has not yet been handed over to the investor for building. Up to date, infrastructure in 4/5 resettlement sites has been finished; residents have received compensation; drawing lots to get land; 16 households in the Dong Bac resettlement region have not received compensation.
Chairman Bui Van Quang and the working group visited the Cam Khe Industrial Park infrastructure project’s field.
Inspecting the reality at the site of the difficulty in land clearance of the Industrial Park as well as the site of building of resettlement sites, Chairman of the Provincial People’s Committee Bui Van Quang praised Cam Khe district’s efforts in clearing land for investment projects and building industrial park infrastructure.
He noted that the initiatives that have attracted local and global enterprises and industries to invest in Cam Khe Industrial Park would greatly contribute to the district’s socioeconomic progress. In the near future, the district must establish that clearing industrial park property is a critical responsibility for the center. From then, the entire political system is mobilized to carry out this duty; in particular, each comrade in the District Party Committee must increase awareness and responsibility to participate, in order to prevent the situation in which site clearance is seen as a private concern of the government.Furthermore, the district must address the working habits and styles of specialized department personnel. Examine and manage personnel work for officers who are not conscientious; Simultaneously, more people should be added to departments, communes, municipalities, and related authorities to expedite site clearance.
To expedite site clearance and project execution, the Cam Khe district must work closely with the Provincial Working Group, departments, and branches. The goal is to make the best possible circumstances for individuals. We will, however, take harsh action against homes who willfully fail to comply. The Chairman of the Provincial People’s Committee further demanded that the district commit to a schedule for completing each project item. Site approval must be completed for the remaining 183 hectares by December 31, 2023.
The Chairman of the Provincial People’s Committee paid a visit to Sunergy Cell Company’s production line, which is undergoing testing in preparation for official operation at Cam Khe Industrial Park.
Households must be organized to draw lots, obtain land, and migrate to the four resettlement zones that have finished infrastructural building. Simultaneously, concentrate on resolving issues in the Dong Bac resettlement region. For the 16 families that have not received compensation, promotion and campaigning will continue; if households do not agree, the procedure of forceful counting and land recovery will be carried out in line with the law.
Chairman Bui Van Quang has directed the Provincial Police to direct specialized departments and district police to coordinate with local authorities to complete documents and develop enforcement implementation plans; Resolutely handle thoroughly, not allowing speculation and expansion to exploit policies. Furthermore, the district police must improve their job in comprehending the situation, guaranteeing security and order, and establishing a climate conducive to healthy investment in the district in general and Cam Khe Industrial Park in particular.
(Source: baophutho.vn)